Summary of Construction Schedule Stewart Creek WWTP Expansion ‐ Phase 1
Notice to Proceed Date: 4‐Jan‐16 Contract days to substantial completion: 583 Days Contract substantial completion date: 9‐Aug‐17 Contract days to final completion: 630 Days Contract final completion date: 25‐Sep‐17
S = F = A = B = C =
Substantial Completion Final Completion Train A substantial completion Train B substantial completion Train C substantial completion
C
A, B
S
Oct‐18
Sep‐18
Aug‐18
Jul‐18
Jun‐18
May‐18
Apr‐18
Mar‐18
Feb‐18
Dec‐17
Nov‐17
Oct‐17
Sep‐17
Aug‐17
Jul‐17
Jun‐17
May‐17
Apr‐17
Mar‐17
Feb‐17
Jan‐17
Dec‐16
Nov‐16
Oct‐16
Sep‐16
Aug‐16
Jul‐16
Jun‐16
May‐16
Apr‐16
Mar‐16
Feb‐16
Jan‐16 Baseline (contract) schedule
Jan‐18
11‐Month contractor delay
21‐Month construction duration per construction contract
F
32‐Month construction duration based on April 2017 schedule update April 2017 Schedule update
C
A, B
S
F
13‐Month delay completing Train C 11‐Month Delay completing A and B 10‐Month delay overall substantial 11‐Month delay in overall final
Page 1 of 1